Report sets out options for acquiring land and
property assets on the Kerria and Tinkers Green regeneration
estates. Report also raises need to commence preparatory work in
relation to the use of Compulsory Purchase Order powers.
Decision type: Key
Reason Key: Substantially / significantly effects 2 or more wards;
Decision status: Recommendations Approved
Wards affected: (All Wards);
Notice of proposed decision first published: 03/10/2014
Decision due: 6 Nov 2014 by Cabinet
Lead member: Leader of the Council
Lead director: Corporate Director Growth, Assets and Environment
Contact: Paul Weston, Assistant Director Assets Email: paul-weston@tamworth.gov.uk.
Consultation process
The acquisition and CPO process will need to
follow a formal legal process. Discussions to take place as part of
the regeneration project board.
Consultees
Regeneration project board
Reason No Public Access: Relates to financial negotiations around the acquisition of land and property Assets.