Capital Outturn Report 2012/13

25/06/2013 - Capital Outturn Report 2012/13

The report of the Portfolio Holder for Operations and Assets seeking to advise members on the final outturn of the Authority’s Capital Programme for 2012/13 (subject to audit confirmation) and requesting approval to re-profile specific programme budgets into 2013/14 was considered.

 

RESOLVED:

 

That:

 

1

the final outturn position of the 2012/13 capital programme be endorsed;

 

2

the budget re-profiling projects into the Authority’s Capital Programme 2013/14 (total £4.778m) be approved, and;

 

3

the consolidation of budgets associated with the Corporate Change Programme totalling £147.7k be approved.

 

 

 