Sandy Way Application

Meeting: 02/03/2021 - Planning Committee (Item 21)

21 Sandy Way Application pdf icon PDF 429 KB

(Report of the Assistant Director Growth and Regeneration)

 

Application no: 0428/2020

Development: Proposed construction of 4No. Employment units (one building) for use within class E (industrial process) B2 (general industry) B8 (storage and distribution) and associated infrastructure.

Location: Land off Sandy Way, Amington, Tamworth

 

Additional documents:

Minutes:

Application Number

 

0428/2020

 

 

Development

 

Proposed construction of 4No. Employment units (one building) for use within use class E (industrial process) B2 (general industry) B8 (storage and distribution) and associated infrastructure

 

Location

 

 

Land off Sandy Way, Amington , Tamworth

RESOLVED

 

Approved subject to the conditions outlined below in accordance with the requirements outlined in the report.

 

 

Conditions / Reasons

 

1

The development shall be started within three years of the date of this permission. Reason: To comply with Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.

 

2

The development hereby approved shall only be carried out in accordance with the application form, the supporting letter and drawing numbers:

 

P401

Site Plan

P400 Rev K

Proposed Site Plan

P402

Site Location Plan

P403 Rev D

Boundary Treatments Plan

P404 Rev D

Surface Treatments

P405 Rev D

Bins and Cycle Hoop Plan

LL1127/001

Lighting Details

P100 Rev B

Floor Plans and Elevations

KL-469-001 Rev P2

Landscape Plan

 

 

Unless otherwise agreed in writing by the Local Planning Authority. Reason: To define the approval.

 

 

CONDITIONS to be complied with PRIOR to the commencement of development hereby approved

 

 

3

No development shall begin until the following elements of a surface water drainage design have been submitted to and approved by the Local Planning Authority in consultation with the Lead Local Flood Authority. The design should be in accordance with the main principles within the Flood Risk Assessment and Drainage Strategy (ref: 62830, 16-09-20, PRK UK Ltd). The design must demonstrate:

 

Surface water drainage system(s) designed in accordance with the Non-technical standards for sustainable drainage systems (DEFRA, March 2015).

SuDS design to provide adequate water quality treatment, in accordance with the CIRIA SuDS Manual Simple Index Approach and SuDS treatment design criteria.

Detailed design (plans, network details and calculations) in support of any surface water drainage scheme, including details on any attenuation system, and the outfall arrangements. Calculations should demonstrate the performance of the designed system for a range of return periods and storm durations. Plans should be adequately labelled to enable comparison with the calculations (e.g. MH and pipe refs).

Plans illustrating flooded areas and flow paths in the event of exceedance of the drainage system. Plans to include FFLs, CLs, relevant GLs and flow arrows.

Provision of an acceptable management and maintenance plan for surface water drainage to ensure that surface water drainage systems shall be maintained and managed for the lifetime of the development. To include the name and contact details of the party responsible.

Reason: To reduce the risk of surface water flooding to the development and properties downstream for the lifetime of the development and to ensure adequate pollution control measures are in place

.

Prior to use/other CONDITIONS to be complied with:

 

4

Prior to their incorporation in to the building(s) hereby approved, details and/or samples of the facing materials to be used shall be submitted to and approved in writing by the Local Planning Authority.  ...  view the full minutes text for item 21