Tamworth Assembly Rooms Project

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: No

Purpose:

To update Cabinet on the progress of the Assembly Rooms Project and to seek relevant approvals to progress the project

Decisions:

The Portfolio Holder for Heritage and Growth updated Cabinet on progress of the Assembly Rooms project and seek relevant approvals to progress the project

 

RESOLVED

That

 

 

1 Cabinet noted the progress of the Assembly Rooms project

 

 

2  Cabinet noted the revised costs as detailed

 

 

3 Cabinet approved the release of £560,000 from the retained Building Repair Fund and delegate spends to Executive Director and Portfolio Holder.

 

 

4 Cabinet approved the supporting plans

 

 

5 Cabinet acknowledged the revised project timetable

 

 

 

(Moved by Councillor D Cook and seconded by Councillor R Pritchard)

 

Report author: Anica Goodwin

Publication date: 04/07/2019

Date of decision: 20/12/2018

Decided at meeting: 20/12/2018 - Cabinet